Project: Power Plant Eemshaven, The Netherlands

Client: Volker Staal en Funderingen B. V.

For the 3rd time, the consortium Arge ViMa entrusts us with special foundation engineering works in this project.

After having secured several building pits with ground anchors, two of our bore and grout crews are now under way to produce tensile Gewi-piles to protect an underwater foundation bottom from uplifing water pressure. Thanks to a precisely attuned overburden drilling procedure, we are able to keep the foundation bottom nearly entirely free of any grout suspension; a circumstance that saves our client significant costs.